Auburn Men’s Basketball Locker Room
Project Overview
White-Spunner Construction was selected as the general contractor to manage the Auburn Men’s Basketball Locker Room Renovation project during the summer of 2019. With less than six months, the locker room was stripped down to the studs and renovated. WSC installed new lockers, graphics, showers, bathrooms, film room, meeting room, athletic training facilities, and press conference area. The renovations included creating a “Hype Room” for players to get ready before taking the court on game days. With less than six months, numerous days blocked out due to graduations, children’s basketball camps, an active campus, and only four parking spots for laydown and staging, this was a challenging site with a compressed schedule.